South Omaha Trail – Sept Update

September 14th, 2015 | Author: Dale Rabideau
Category: Trails | Tags:

Christopher Burbach of the Omaha World Herald wrote up an article on the coordination between the CSO (Clean Solutions for Omaha), which separates storm sewer from sanitation sewer, and construction of the South Omaha Trail.

With drier weather, Vrana is moving dirt, pouring cement, building retention walls and water detention chambers. Here are some pictures showing the progress:

West end of sidepath on D St

West end of sidepath on D St

D and 38 St a couple days ago

D and 38 St a couple days ago

D and 38 St today

D and 38 St today

D St sidepath looking west

D St sidepath looking west

Below shows the old curb and storm sewer juxtaposed with the new curb, i.e. the street diet plus a couple feet of land to fit in the 8′ wide sidepath trail. The rest of South Omaha Trail is 10′ wide.

End of D St looking east

End of D St looking east

Prep for retention wall at east end of D St

Prep for retention wall at east end of D St

Trail to 36th St at 5% grade

Trail to 36th St at 5% grade

blocks for the retaining wall

blocks for the retaining wall

moving dirt

moving dirt

Retaining wall just west of 36th St a couple days ago

Retaining wall just west of 36th St a couple days ago

Looking west from 36th St

Looking west from 36th St

Trail side of wall east of 36th

Trail side of wall east of 36th

Looking north under I-80 viaduct

Looking north under I-80 viaduct a couple days ago

Looking west from south of I-80 viaduct a couple days ago

Looking west from south of I-80 viaduct a couple days ago

Spot of previous picture today

Spot of previous picture today

Big toys for big boys and girls

Big toys for big boys and girls

Hauling dirt from water detention chambers

Hauling dirt from water detention chambers

Water detention area

Water detention area

sept pic 07

The stake marks the width yet to be dug out

The stake marks the width yet to be dug out

Water detention chambers will go north to front end loader (almost Vinton St)

Water detention chambers will go north to front end loader (almost Vinton St)

Great to see all the workers, equipment, and dirt moving and making progress!

Previous posts on South Omaha Trail:
August Update
July Update
June Update
March Update
Initial Post with Overview

Omaha Bikes

info@omahabikes.org
1516 Cuming Street | Omaha, NE 68102
Twitter

Latest Tweet


Twitter: omahabikes

Twitter

Can't Find It?

Get'ch yo search on!

Get Connected

Newsletter

E-mail Signup

Stay up to date, sign up for updates from Omaha Bikes.
Made possible by funding from the Department of Health and Human Services
© Copyright 2017 | Omaha Bikes | Site by Grain & Mortar